Quantcast
Viewing all articles
Browse latest Browse all 9760

Re: CK11N Costing Run

Yes check the Strategy Sequence in your costing variant, More importantly Check when did you changed the price? The screenshot shows the FG may have already a valid cost which is valid for the period, if you changed a price recently and did not re-org the cost using CKR1. The cost will not update the current price when there is a current cost which is valid for the period.

 

You have to re-org the cost using CKR1 and then re-run the Standard Costing using CK11n and it should update the current price based your strategy sequence.

 

BR

Hrushikesh


Viewing all articles
Browse latest Browse all 9760

Trending Articles