Hello All,
I am getting this issue in VL01N, "No schedule lines due for delivery up to the selected date" And i have searched in forum about this issue. But after referring to previous threads i got some doubts.
Here i have some doubts
- In sales order schedule line tab why schedules have split in two dates. one with confirmed quantity and another without.
- If i select the date with confirmed quantity in VL01N. It dose not show the delivery quantity. and if i give quantity manually. it says "only 0 PC of material available".
- Even if i put the future date in VL01N, it says "only 0 PC of material available".
I have checked.
- In VOV8 no lead time has been given.
Kindly help me out to understand this issue and over come it.
Regards,
Manoj