Hello Experts!!!
I have installed the IDES for MM Module, as you people are aware the company code, plant and other org levels were already created.
Now while i created a PO and tried to do the GR with reference i got the following error:
"Posting period 009 2014 is not open"
Previously I used to work as an end user for MM & PS module, but was a beginner. The posting date in the MIGO screen by default was the date for tomorrow.
i.e. if today i wanted to process ( 08.09.2014 ) the default date of posting was 09.09.2014, and on "check" it showed OK but while on posting it showed the subject error.
Need advice please.
I read the previous discussion on the same matter and could not find the solution.
Looking forward to have the solution.
Romit